Pluit City Dredging and Land Development

ClientJoint Operation Boskalis Van Oord
Period2015 - present

Dredging Works

  • Sand key dredging 3,000,000 mᶟ (70% dredging works were performed by East Marine Pte Ltd and 30% was done by PT Timur Bahari)
  • Access channel dredging 50,000 mᶟ
  • Chiseling breakwater concrete slab core 1,200 m
  • Removal of existing breakwater 1,200 m